Shannon 39 2007
  • Built for Ken Lubin
  • Construction details and
  • Lay up Schedule
2
All fiberglass and core material is measured, pre cut, and sorted according to lay-up schedule
3
Hull - List of materials and
 lay-up schedule
4
Deck - List of materials and
 lay-up schedule
5
Deck Mold, ready for gelcoat
6
Deck Mold, Cockpit section
7
Deck Mold, Mid section
8
Deck Mold, Entire deck before release
9
Deck Mold, Bow Section
10
Deck Mold
Trimming of deck just before mold release.
11
Deck, Aft section after release
12
Deck
Cockpit section after release
13
Deck
Entire deck after release
14
Trimming of deck just before mold release.
15
Hull
Mold ready for lay-up
16
Hull
First day of Lay-up
17
Glass shop manager with sample of core material
18
Hull
Hull after release from mold
19
Hull
Hull moved to carpentry shop
20
Hull
After section as carpentry
work begins.
21
Hull
Mid section as carpentry
work begins.
22
Hull
Forward section as carpentry
work begins.
23
Hull
Forward section in December
24
Hull
Forward section in January
25
Hull
Forward section in February
26
Hull
Forward section in February
27
Hull
Forward section in March
28
Hull
Forward section in April
29
Hull
Keel Layup

  • The keel is an integral part, and is molded to the hull. The keel supporting structure (skin, there are no keel bolts used) is comprised of twenty four layers of 2408 inter woven to the structure of the hull during hull lay-up.  See arrows at right to note termination of keel weave.
30
Keel
Lead ballast pieces